Date agreed | 24/06/2019 |
---|---|
Date to be reviewed | 06/04/2023 |
Satisfaction with cleaning |
2018 to 2019 (Actual) 80% |
2019 to 2020 (Actual) 85.7% |
2020 to 2021 (Actual) 76.2% |
2021 to 2022 (Actual) 62.1% |
---|---|---|---|---|
Satisfaction with grounds maintenance |
2018 to 2019 (Actual) 84% |
2019 to 2020 (Actual) 85.7% |
2020 to 2021 (Actual) 92.9% |
2021 to 2022 (Actual) 83.3% |
Action | Due date |
---|---|
Demolish redundant sheds and replace with cycle storage | 30/09/2022 |
Add bollards to front of some of the blocks to ensure access and exit safely | 23/02/2023 |
Action | How it was achieved | Delivered on |
---|---|---|
Raise works order for blocked drains to be cleared | Works order raised for drains to be cleared by mid Dec 2019 | 30/11/2018 |
Works orders will be raised to repair all vandalised security doors and windows. | Works order raised | 30/11/2018 |
Arrange a resident meeting with TRA and advertise the Safer Neighbourhood Team Panel meetings. | Attended a Meeting with the police , councillors , and residents regarding the ASB on estate. Police will be doing more patrolling. | 25/02/2019 |
Liaise with Pinnacle cleaning contractor to monitor and reduce graffiti | Graffiti had been cleared from the blocks on Mountearl Gardens | 28/02/2019 |
Organise a visit between Caretaker and Technical Team to identify faulty lights. | Lights have been restored. | 13/09/2019 |
Arrange renewal or repair of bin chamber door | Works order raised | 30/11/2018 |
Obtain a quote from Mears for bollards to be put on Pavement 13-26 Adare Walk to stop cars parking. | Installation of Bollards has been completed | 12/06/2019 |
Renew signage to blocks which has faded over time | Block and Estate signage was installed/complete by 07/02/2020 | 07/02/2020 |
Add bays and lines to ensure bins are collected and dangerous parking is reduced. | Lines and cross hatches installed across the site to reduce dangerous and obstructive parking. | 21/04/2021 |